StarAgile
Oct 10, 2024
4,885
20 mins
PERT is the tool which will help you to sort out the activities by calculating the real schedule and to find out many events and milestones of every activity that we do.
Ever thought of how to solve the problems in real life? Ever wondered when you go shopping on how to complete all the activities in the best possible way. Then you are reading the right blog, in this blog, we will discuss how to manage complex things easily and simply. It does not only apply to daily life scenarios but also to work-life where you can use this tool to solve problems and complex scenarios by using this tool.
Yes, we are talking about the tool which will help you to sort out the activities by calculating the real schedule and to find out many events and milestones of every activity that we do.
Yes we are talking about the PERT tool. After reading this blog you will understand how to use the PERT tool to solve many problems. To know more about the PERT tool you can register for the PMP certification online.
It is one of the tools used to manage the project management dependencies
The project is a series of complex activities that are interdependent to make it successful. These series and parallel tasks form the network diagram.
Project tracking is important in managing projects and PERT is used in evaluation and review.
PERT, a network diagram in which the activities and milestones are embodied on the line nodes respectively.
The sample PERT is shown as a diagram below.
The difference between the critical path method (CPM) and PERT is the former one uses the fixed time estimates for the activities and does not consider the variations in the time. It only helps us to determine the longest path or the critical path in the network diagram. However, the latter one uses the randomness in the time completion.
In PERT the nodes are numbered by 10 as any other activity can be inserted between the nodes without changing the network diagram itself. The activities are labeled as alphabets with the expected time to complete the activity. To know more learn about PMP online training.
1.Optimistic Time (OT) - This time is the shortest possible time to complete the projects. It is the 3 standard deviations from the mean that is it has approximately 1% chance that the project gets completed at this time.
2. Most Likely Time (MLT) - This is the time which has the highest possibility of the completion
3. Pessimistic Time (PT) - It is the longest possible time for activity completion. Again the 3 Standards deviations from the mean are used to calculate the pessimistic time.
The PERT assumes the beta probability distribution to complete the time estimates. These are calculated as Expected time and the formula is,
Expected Time (ET) = (OT + 4 * MLT + PT) / 6
The ET is shown in a network diagram.
Variance = 6 SD (standard deviations) between the OT and PT as shown below
[(PT - OT / 6]2
Critical path determination – It is the longest possible time to complete the project. We need to find the four quantities in determining the critical path they are the Earliest Start Time, Earliest Finish Time, Latest Start Time, and Latest Finish Time. They are calculated by using the Expected time of each activity. The Earliest Start and Finish time are calculated by working forward on the network diagram. The Latest Start and Finish time are calculated by working backward on the network diagram.
Updating the diagram - As the execution starts, the PERT diagram is updated by the actual time to see what the deviation is. In case there are delays then additional resources are put to manage the time.
You can learn more about this tool by doing a PMP certification course.
The total float (TF) is the thing to determine how long the activity can be delayed without modifying the project completion date. On the critical path, the total float is zero. Total float and slack can be used interchangeably.
There are 2 methods to calculate the total float.
TF = Late – Early (both are start dates)
Or
TF = Late - Early (both are finish date)
Free float (FF) is determined as to how long the activity can be delayed without delaying the early start date of the successor activity.
FF = ES of next activity - EF of the current activity.
The project manager is responsible for doing the PERT analysis and if you want to do it yourself look for the project manager certificate online.
The PERT chart helps a great deal in resolving the complex project into smaller activities with expected timelines. Once you have the PERT that works for you, the activities and timelines will ensure that you are cutting down on the timelines and meet the target within the project completion date. Once you are meeting the timelines then you are cutting down on the cost on the operations and ensure you are not penalized for the late delivery of the projects.
Take up the scenario of software development for making an application where you need to break down the development, test, and production activities into smaller features based addition activities. You can use the PERT network diagram to sequence and write the timelines for each software development life cycle activities as shown in the diagram below.
When to draw a PERT network chart with a website construction example is as shown below,
Understood what is pert in project management, now know the difference between PERT and CPM.
PERT is used extensively in the manufacturing industry with great success and from the past 2 decades, the PERT is used in the IT, Embedded systems, Hi-Tech, and software industry. It has helped many companies in managing projects to produce products or services in a timely fashion.
CPM is part of PERT and PERT is a broader topic that helps the project manager in managing the schedule by calculating the critical path, the floats, and slack period and estimating the expected time from the optimistic, pessimistic, and most likely time.
The CPM is just used to find the longest path it takes to complete the project which is the critical path. PERT is based on the events based, uses a probabilistic model, unpredictable activities and three-time estimates whereas CPM is activity-based, uses a deterministic model, for predictable activities, and uses one time estimates.
Are you curious to learn PERT in a real-time scenario then why wait? Do register for training with StarAgile for the PMP certification training course.
professionals trained
countries
sucess rate
>4.5 ratings in Google